CS4500 Weekly Management Report
3/30/2009
Project Status
First Release posted to team website. This includes all must have features and a
couple
of nice to haves.
We are working on optimization of the drawing system for our second
release. Investigation into flattening out objects into
bitmaps is proceeding. UI modifications
for nice to haves and improved usability are the main
focus of this sprint.
Accomplishments
Team – Started Fourth sprint
-Second release coming up
Tim – Continued optimization of drawing manager(Bitmap
investigation).
Implemented
updates to layer handling to help with preferences
Adam
– Changed implementation of saved preferences to be layer based
Worked on Bugs related to
Preferences screen
Curtis
- Worked on UI changes as requested by
sponsor
Delivered his first baby!!
Josh – Updated
VVR document and handed in
Tested code for new Draw UI behaviors
Reviewed Drawing Manager(Bitmap model).
Scott
– Provided ability to scale image to match Printer resolution.
Print preview updated to display
partial image to work with Zoom on UI.
Goals & Priorities
● Short
○
Complete work on VVR 2 document due 4/3 [Curtis, Adam]
-Deliverable: Rough draft due
3/31
○
Present Release build 2 during meeting with Prof. Brunvand 4/7 [Tim, Adam]
-Deliverable: Successful review
with all features and nice to haves
○
Review POC for 4/7 [Josh, Adam, Tim]
-Deliverable: Optimized drawing
model that allows for loading large files.
○
Continue QA process for application 4/7 [Adam, Curtis, Josh]
-Deliverable: Complete runs of
all test plans, log bugs in Bugzilla
○
Print preview and print scaling – Present to Team 4/1 [Scott, Josh]
○
Implement additional User Interface features as specified by Customer 4/5
[Curtis]
-Deliverable: New buttons (Show
all levels) (OK/Cancel on preferences)
● Long
○ Print test file on Epson plotter 4/5(delayed) [Scott, Curtis]
○ QA testing and verification for release 2
Complete 4/7. [Adam, Curtis, Josh]
Needs
None currently