CS4500 Weekly Management Report

2/9/2009

 

Project Status

            We have completed our investigations into the GDS II format and printer drivers. We have also

                completed our first sprint, with a POC to review with our customer.

 

Accomplishments

                Team – Completed first sprint

                                -POC for handling GDS II files, and print drivers

                Tim – Completed POC for alpha blending and color shifting.

               

                Adam – Documented GDSViewer product for review by team.

                              Created C# solution with GDS classes and objects.

                              Worked on SRS document

Curtis - Documented GDS Viewer 2.1's

(http://www.gbresearch.com/gdsviewer/Default.aspx)

                                Worked on SRS document

                Josh – Worked on SRS Document

                            Completed UML diagram for GDS objects.

Scott – Completed work on printer driver investigation.

             Provided documentation on printers for SRS document.

 

Goals & Priorities

● Short

○ Complete work on Software Requirements Specification due 2/10 [Curtis, Adam]

                -Deliverable: Final Draft by 2/10

○ Complete OpenGL POC for meeting with Prof. Brunvand 2/10 [Tim, Adam]

                -Deliverable: Working POC for meeting

○ Provide feedback to team from investigation due 2/3 [Curtis, Adam]

                -Deliverable: Guidelines for interactions with GDS files and general viewer behaviors.

○ Provide initial POC for loading GDS files 2/17 [Adam, Josh]

                -Deliverable: C# solution that is able to load GDS files and store them in memory as .Net objects.

○ Complete work on Software Design Specification due 2/13 [Scott, Curtis]

                -Deliverable: Rough Draft by 2/10.

○ Develop POC for printing to Epson printer 2/17 [Scott, Curtis]

                -Deliverable: C# solution that is able to print on the Epson printer with all dialog options.

● Long

            ○ Integration of File loading, Viewing and Printing for final solution.  2/27(Sprint 2)  [Adam, Tim]

            ○ QA testing and verification Begin 2/28. [Adam, Curtis, Josh]

Needs