CS4500 Weekly Management Report
2/23/2009
Project Status
We have completed our second sprint, which will end up
being the core of our application.
Our scheduled meeting with Prof. Brunvand
on Tuesday should prove out our efforts so far
in getting this app ready. We have covered off on all of the points that
were raised during our
previous meeting, and feel
confident that we can take on some nice to haves soon.
Accomplishments
Team – Completed Second sprint!
-POC for opening GDS files and
drawing them. We even got print support!
Tim – Developed frontend interface for selecting
color palettes and alpha transparency.
Successfully drew our first GDS object based on the parsed objects! With Color and Alpha!
Worked on format for saving color and alpha settings for GDS file
Adam
– Continued work on GDS parser and Object model w/ Tim
Received training on Draw Manager
from Tim
Worked
on SDS v2 document [Draw Manager section]
Curtis
- Worked on SDS v2 document [UI section]
Provided mockup of UI based on
similar products
Josh – Worked on SDS v2 Document [GDS Parser section]
Continued
work on GDS parser and object model.
Scott
– Worked on SDS v2 Document [Print Manager section]
Added print support to
application!
Worked on format for saving color and alpha
settings for GDS file
Goals & Priorities
● Short
○
Complete work on VVP document due 2/27 [Curtis, Adam]
-Deliverable: Rough draft due
2/24
○
Present POC during meeting with Prof. Brunvand 2/24
[Tim, Adam]
-Deliverable: Successful review
○
Continue work on final version of library for loading GDS files 2/27 [Adam,
Josh]
-Deliverable: Updated object
model based on team suggestions 2/26
○
Develop app Library for printing to Epson printer 2/24 [Scott, Curtis]
-Deliverable: C# library that
can be plugged into our final app.
○
Review POC for 2/24
[Josh, Adam, Tim]
-Deliverable: Merged C# solution
that contains work from both teams.
○
Begin QA process for application 2/28 [Adam, Curtis, Josh]
-Deliverable: Test plans
completed for review on 3/3
○
Start Sprint 3 – Branch to final working app, and formalize the structure of
the application. [Tim, Adam, Josh, Curtis, Scott]
-Deliverable: Structured and fully documented application framework
● Long
○ Develop User Interface look and feel 3/10
[Curtis]
○ Print test file on Epson plotter 3/10 [Scott, Curtis]
○ QA testing and verification Complete
3/31. [Adam, Curtis, Josh]
Needs
None currently