CS4500 Weekly Management Report
3/09/2009
Project Status
Things are progressing well for our first code drop.
Tim's efforts on the Graphics engine have been
a huge benefit to our product. With the UI updates and features that we've
been adding, the first drop
should be very usable, and user friendly.
We are still focused on getting the application ready
for the first release.
Accomplishments
Team – Finishing Third sprint
-Final product for First Release on
3/13
Tim – Updated Drawing/Graphics to recursively draw
Structures in refs.
Completed rotation and flipping of structures
Optimized code for
greater redraw rate.
Adam
– Completed work on Preferences UI that will allow user to save color/alpha
options
Curtis
- Completed work on Preferences UI that
will allow user to save color/alpha options
Worked on VVP document [Sections
2 & 3]
Josh – Worked on code for drawing text/fonts in
OpenGL for Text objects
Scott
– Continued work on Print integration, and memory management.
Worked on optimizations for
print driver that will allow for handling large images.
Goals & Priorities
● Short
○
Complete work on VVR document due 3/13 [Curtis, Adam]
-Deliverable: Rough draft due
3/10
○
Present POC during meeting with Prof. Brunvand 3/10
[Tim, Adam]
-Deliverable: Successful review
with all sub features
○
Review POC for 3/10 [Josh, Adam, Tim]
-Deliverable: Merged C# solution
that contains work from both teams.
○
Continue QA process for application 3/12 [Adam, Curtis, Josh]
-Deliverable: Test plans
executed by 3/12
○
Finish Sprint 3 – Branch to final working app, and formalize the structure of
the application. [Tim, Adam, Josh, Curtis, Scott]
-Deliverable: Structured and fully documented application framework
● Long
○ Implement additional User Interface features
as specified by Customer 3/24 [Curtis]
○ Print test file on Epson plotter 3/24(delayed) [Scott, Curtis]
○ QA testing and verification Complete 3/31.
[Adam, Curtis, Josh]
Needs
None currently